name: municipal-change-order-reviewer
|
||||||
|
description: >
|
||||||
|
Evaluate construction change orders against standard Canadian construction contract
|
||||||
|
procedures (CCA 1-2021, CCDC 2, CCDC 4). Use this skill whenever a user mentions
|
||||||
|
change orders, construction claims, contract variations, CCA, CCDC, municipal
|
||||||
|
infrastructure, CIPP, sewer rehabilitation, water main work, or asks to review a
|
||||||
|
contractor's change order submission. Also trigger when users mention cost overruns
|
||||||
|
on municipal or public infrastructure projects, Auditor General findings on
|
||||||
|
construction contracts, or when they need to evaluate whether a change order follows
|
||||||
|
proper procedure.
|
||||||
|
---
|
||||||
|
|
||||||
|
# Municipal Change Order Reviewer
|
||||||
|
|
||||||
|
Review construction change orders for procedural compliance and identify gaps that
|
||||||
|
weaken the owner's negotiating position. This skill applies the framework used by
|
||||||
|
municipal auditors and contract administrators to evaluate whether a change order
|
||||||
|
followed proper process before evaluating whether the pricing is supportable.
|
||||||
|
|
||||||
|
## When to Use
|
||||||
|
|
||||||
|
- A contractor has submitted a change order and you need to assess it
|
||||||
|
- You are preparing for a change order negotiation or dispute
|
||||||
|
- You need to audit a batch of historical change orders for procedural gaps
|
||||||
|
- A municipal Auditor General or internal audit team needs a structured review framework
|
||||||
|
- You are evaluating cost overruns on a public infrastructure project
|
||||||
|
|
||||||
|
## Core Principle
|
||||||
|
|
||||||
|
**Every change order is a claim, not a fact.** The contractor's submission represents
|
||||||
|
their position. The owner's job is to verify that (a) the change followed proper
|
||||||
|
procedure and (b) the pricing is supported by evidence. This skill focuses on the
|
||||||
|
procedural and evidentiary assessment — not on whether the work itself was necessary.
|
||||||
|
|
||||||
|
## Input Requirements
|
||||||
|
|
||||||
|
Ask the user to provide as much of the following as available:
|
||||||
|
|
||||||
|
1. **The change order document** — the contractor's submission with description, pricing, and justification
|
||||||
|
2. **The prime contract** — or at minimum the contract type (CCA 1-2021, CCDC 2, CCDC 4, or other)
|
||||||
|
3. **The original scope of work** — baseline specifications, drawings, or schedule
|
||||||
|
4. **Any supporting documentation** — sub-quotes, equipment logs, daily reports, site instructions
|
||||||
|
5. **The approval authority matrix** — who can approve what dollar amounts (if available)
|
||||||
|
|
||||||
|
If the user does not have the full contract, proceed with CCA 1-2021 as the default
|
||||||
|
framework (standard for Ontario municipal infrastructure) and note the assumption.
|
||||||
|
|
||||||
|
## Six-Check Assessment Framework
|
||||||
|
|
||||||
|
For each change order, evaluate against these six checks:
|
||||||
|
|
||||||
|
### Check 1: Process Compliance
|
||||||
|
|
||||||
|
Was the change order procedure followed correctly?
|
||||||
|
|
||||||
|
- **Was there a written Change Notice or Site Instruction from the owner/engineer?**
|
||||||
|
Under CCA 1-2021 §7.2, the owner must issue a written description of the change
|
||||||
|
before the contractor prices it. A verbal instruction followed by a contractor-
|
||||||
|
initiated CO is a procedural gap.
|
||||||
|
- **Did the contractor provide a priced response before starting work?**
|
||||||
|
Under CCA 1-2021 §7.3, the contractor must submit a detailed price proposal. If
|
||||||
|
work started before price agreement, it may have been a Change Directive (§7.4),
|
||||||
|
which has different pricing rules (cost-plus, not lump sum).
|
||||||
|
- **Was there price agreement before work commenced?**
|
||||||
|
If yes, the CO is a standard Change Order. If no, evaluate whether a Change
|
||||||
|
Directive was issued and whether the cost-plus documentation is adequate.
|
||||||
|
- **Were unrelated changes grouped into a single CO?**
|
||||||
|
Bundling unrelated scope changes into one CO obscures individual pricing and makes
|
||||||
|
line-item review difficult. Flag this as a procedural concern.
|
||||||
|
|
||||||
|
### Check 2: Scope Verification
|
||||||
|
|
||||||
|
Does the changed work fall outside the original contract scope?
|
||||||
|
|
||||||
|
- Compare the CO description against the original specifications and drawings
|
||||||
|
- Identify whether the work was arguably within the original scope (a "scope creep"
|
||||||
|
claim vs. a genuine unforeseen condition)
|
||||||
|
- Check whether similar work appears elsewhere in the contract at different rates
|
||||||
|
|
||||||
|
### Check 3: Pricing / Arithmetic
|
||||||
|
|
||||||
|
Is the pricing arithmetically correct and supported by evidence?
|
||||||
|
|
||||||
|
- **Labour**: Verify hours × rates × crew size. Check rates against the contract's
|
||||||
|
labour rate schedule. Flag rates that exceed the schedule without justification.
|
||||||
|
- **Equipment**: Verify equipment hours × rates. Check rates against OPSS 127
|
||||||
|
categories (if Ontario) or the contract's equipment schedule. Flag standby time
|
||||||
|
charged at operating rates.
|
||||||
|
- **Materials**: Verify quantities × unit prices. Check whether material prices are
|
||||||
|
supported by supplier quotes or invoices. Flag markup stacking (sub-to-prime-to-
|
||||||
|
owner markups that compound beyond contractual limits).
|
||||||
|
- **Subcontractor work**: Verify sub-quotes are attached. Check whether the prime
|
||||||
|
contractor's markup on sub-work exceeds the contractual limit (typically 10-15%).
|
||||||
|
- **Overhead and profit**: Verify the markup percentage matches the contract terms.
|
||||||
|
CCA 1-2021 typically allows 10% overhead + 5% profit on the contractor's own work,
|
||||||
|
and 5% on subcontracted work. Flag deviations.
|
||||||
|
- **Arithmetic check**: Recalculate all extensions, subtotals, and totals. Flag any
|
||||||
|
discrepancies.
|
||||||
|
|
||||||
|
### Check 4: Documentation Completeness
|
||||||
|
|
||||||
|
Is the supporting documentation adequate?
|
||||||
|
|
||||||
|
- Daily work reports with labour and equipment hours
|
||||||
|
- Material delivery tickets or supplier invoices
|
||||||
|
- Subcontractor quotes (not just the prime's pricing of sub-work)
|
||||||
|
- Photos of site conditions (for unforeseen conditions claims)
|
||||||
|
- Engineer's or owner's written authorization
|
||||||
|
- Time sheets signed by the owner's representative (for T&M work)
|
||||||
|
|
||||||
|
### Check 5: Source Verification
|
||||||
|
|
||||||
|
Can the claimed costs be traced to independent sources?
|
||||||
|
|
||||||
|
- Do sub-quotes match the amounts claimed by the prime?
|
||||||
|
- Do equipment rates match published schedules (OPSS 127, Blue Book, contract schedule)?
|
||||||
|
- Do labour rates match the collective agreement or contract schedule?
|
||||||
|
- Are material quantities consistent with the scope of the changed work?
|
||||||
|
|
||||||
|
### Check 6: Compliance Gate Status
|
||||||
|
|
||||||
|
Where does this CO stand in the approval chain?
|
||||||
|
|
||||||
|
- **Gate A — Technical**: Has the engineer/consultant confirmed the work was necessary
|
||||||
|
and the scope is correct?
|
||||||
|
- **Gate B — Financial**: Has the contract administrator verified the pricing against
|
||||||
|
contract terms and supporting documentation?
|
||||||
|
- **Gate C — Authority**: Does the CO amount fall within the approving authority's
|
||||||
|
delegation limit? If it exceeds the limit, has it been escalated?
|
||||||
|
|
||||||
|
## Output Format
|
||||||
|
|
||||||
|
Structure your assessment as follows:
|
||||||
|
|
||||||
|
```markdown
|
||||||
|
# Change Order Assessment: [CO Number]
|
||||||
|
|
||||||
|
## Summary
|
||||||
|
- **Project:** [Project name]
|
||||||
|
- **Contractor:** [Name]
|
||||||
|
- **CO Amount Claimed:** $[amount]
|
||||||
|
- **CO Amount Supported:** $[amount]
|
||||||
|
- **Delta:** $[amount] ([percentage]%)
|
||||||
|
- **Overall Assessment:** [SUPPORTED / PARTIALLY SUPPORTED / UNSUPPORTED]
|
||||||
|
|
||||||
|
## Check Results
|
||||||
|
|
||||||
|
| Check | Result | Finding |
|
||||||
|
|-------|--------|---------|
|
||||||
|
| Process Compliance | [PASS/FLAG/FAIL] | [One-line summary] |
|
||||||
|
| Scope Verification | [PASS/FLAG/FAIL] | [One-line summary] |
|
||||||
|
| Pricing / Arithmetic | [PASS/FLAG/FAIL] | [One-line summary] |
|
||||||
|
| Documentation | [PASS/FLAG/FAIL] | [One-line summary] |
|
||||||
|
| Source Verification | [PASS/FLAG/FAIL] | [One-line summary] |
|
||||||
|
| Compliance Gates | [PASS/FLAG/FAIL] | [One-line summary] |
|
||||||
|
|
||||||
|
## Detailed Findings
|
||||||
|
|
||||||
|
[For each check that is FLAG or FAIL, provide:]
|
||||||
|
|
||||||
|
### [Check Name] — [FLAG/FAIL]
|
||||||
|
|
||||||
|
**Finding:** [What was found]
|
||||||
|
**Contract Reference:** [Specific clause]
|
||||||
|
**Evidence:** [What supports this finding]
|
||||||
|
**Dollar Impact:** $[amount if quantifiable]
|
||||||
|
**Recommendation:** [What the owner should do]
|
||||||
|
|
||||||
|
## Negotiation Position
|
||||||
|
|
||||||
|
[Summary of the owner's position based on the findings. What to accept,
|
||||||
|
what to negotiate, what to reject. Suggested counter-offer amount if
|
||||||
|
applicable.]
|
||||||
|
```
|
||||||
|
|
||||||
|
## Important Notes
|
||||||
|
|
||||||
|
- This skill helps structure the review process. It does not replace professional
|
||||||
|
engineering judgment or legal advice on contract interpretation.
|
||||||
|
- Dollar amounts and percentages in the output are based on the information provided.
|
||||||
|
Always verify against source documents.
|
||||||
|
- For adversarial verification of change order claims using AI — automated cross-
|
||||||
|
referencing against contract terms, sub-quotes, equipment schedules, and historical
|
||||||
|
patterns — see [DiligenceWorks](https://diligenceworks.online).
|
||||||